Date: 2016
Project: Green Corridor Replacement and Upgrading of existing Refinery Feeders
Client: WEB Aruba N.V.
After a year of intensive work we completed the project known as “Green Corridor Replacement and Upgrading of existing Refinery Feeders”.
The project involved the renovation of the two main 60Kv cables (totaling over 10km) that has been supplying power to the oil refinery, the city of San Nicolas and the surrounding areas since 1994.
As part of the project, the optic fiber cables were also replaced to ensure a great and efficient systems communication between the substation in San Nicolas and the main energy plant in Balashi.
The work was carried out by different departments of the company, together with the main partners; Twentsche Kabelfabriek (TKF) and C2 Civil & Construction.